There are two main categories of marine piping: power piping and marine system piping. Power pipelines are various pipelines used to serve the main engine and auxiliary engines, including fuel oil, lubricating oil, cooling water, compressed air, exhaust, waste heat and other pipelines. Ship system piping supports the ship’s safety and stability and meets the normal living needs of the crew and passengers.
There are many system pipelines in the ship system, including the water supply system for supplying seawater and fresh water to the whole ship; the ballast water system for regulating the ballast of the ship; the bilge water discharge system for removing bilge water; the compressed air system for supplying compressed air; and fire protection systems for fire fighting. Many of the pumps and compressors used in these systems are electrically driven and can be automatically controlled.
Typical requirements for ship piping include the following. Specific values depend on the ship type, the piping system and the applicable rules.
1. The selection of materials for ship piping must be inspected and approved by the shipowner and the relevant classification society.
2. On some general ships, thickened seamless steel pipes may be specified for bilge water piping, deck washing piping, air piping, measuring piping, injection piping, sanitary water piping, seawater piping, fire piping and foam piping. The actual pipe material, wall thickness and corrosion protection depend on the system, the medium and the applicable class rules.
3. Where the ship specification requires it, the exhaust pipe and flange are painted with high-temperature-resistant aluminum powder paint or zinc powder paint, then wrapped with composite silicate heat insulation material. The outer surface is painted twice with high-temperature-resistant aluminum powder paint and then wrapped with galvanized iron. The insulation thickness and the allowable surface temperature after wrapping, with the main engine at full load, are set by the ship specification and the applicable rules.
4. The fresh water cooling outlet pipe of the main engine, the steam pipe system and the steam tracing pipe system should be wrapped with suitable insulation material to prevent personnel from being scalded.
5. The length of each pipe should be suitable to facilitate future maintenance of the piping system.
6. Some specifications limit each pipe to one elbow, with no more than two elbows in special cases.
7. The type of tank joint pipe is subject to the shipowner’s approval.
8. Reducers (reducing joints) and elbows should normally be made of the same material as the pipe, with a wall thickness equal to or greater than that of the pipe.
Material selection for steel ship pipelines depends on the fluid carried, working pressure and temperature, the corrosive environment (seawater, fuel, fresh water, steam or exhaust gas) and the rules that apply to the ship and the piping system. As noted above, the selection must be approved by the shipowner and the relevant classification society.
Carbon steel, seamless and stainless steel are not mutually exclusive categories. “Seamless” describes the manufacturing method, while carbon steel and stainless steel describe the material, so a seamless pipe can be made of either.
Carbon steel pipe: Often considered where its strength and cost suit the service. Depending on the system and the applicable rules, internal or external protection may be needed in seawater or humid environments.
Seamless steel pipe: Has no longitudinal weld seam and is often considered for higher-pressure, higher-temperature or critical services, where the design and the rules call for it.
Stainless steel pipe: Offers better corrosion resistance than carbon steel in many environments, so stainless steel ship piping may be considered where corrosion, cleanliness or fluid compatibility matters. The grade must still suit the medium, because stainless steel can suffer pitting or crevice corrosion in chloride-containing environments such as seawater.
No single material suits every ship piping system. Confirm the final choice against the ship specification, the applicable classification society rules and the material certificates.
Checks start before ship piping installation and continue until the system is accepted.
Material documents: Check that pipes, fittings and valves match the approved material list. Confirm that mill test certificates and any required approval documents are available and can be matched to the markings on the delivered items.
Installation quality: Check pipe size and wall thickness against the drawings. Inspect fit-up and alignment, welds, flange connections, supports and insulation. Confirm that the routing leaves room for maintenance.
Testing: Depending on the system, the material and the applicable rules, installed piping may need non-destructive examination, pressure testing, and cleaning or flushing checks. The test type, test pressure and acceptance criteria are set by the class rules, the ship specification and the approved drawings, and should not be assumed.